A MAJOR sewer upgrade, which has affected business and caused traffic tailbacks, is to be halted after it emerged there was a more urgent need for work elsewhere in the Island.
The next phase of sewer upgrades north of Sion will need to be paused as staff and resources are diverted to work needed to support a 30-home affordable housing development at Maufant.
Infrastructure Minister Jonathan Renouf said money allocated to Phase 1C of the northern sewer network programme would instead be used to prioritise upgrades at Maufant, where planning permission has been granted for the homes.
Ellen Gallichan, group director of Operations, Transport and Sport told the panel that the Maufant works could go on until 2029 – despite the development of the housing project due to begin in 2028.
She explained that they will be “very mindful to try and minimise disruption” to businesses and residents in the area, “learning” from parts of the St John’s projects.
The decision means the current phase of the St John works – which began in November 2025 – will be completed but the next portion of the upgrades further north will not take place as planned.
The St John works have left some businesses in the area facing difficulties attracting customers, with one store owner previously stating that she worried that the impact of the works could be “similar to that of Covid”. She added that the lanes were “littered with one-way and no-entry signs and arrows” which “don’t tell you anything”.
Deputy Renouf told the Environment, Housing and Infrastructure budget review hearing that the department was making a “significant adjustment” to its investment in sewer upgrades.

Panel chair Deputy Hilary Jeune asked whether this meant Phase 1C north of Sion would be stopped for now.
Deputy Renouf replied: “For now, yes, because there’s a more pressing need at Maufaunt.”
He said postponing the next stage would bring some relief to those affected by the existing roadworks.
The announcement followed a question from panel member Deputy Alex Curtis about whether planned investment in liquid-waste infrastructure still matched the need for upgrades and capacity for new housing.
The Maufant development, on La Rue des Buttes just south of St Martin’s Catholic Church, was approved after the former Planning Committee’s refusal in March 2025 was overturned on appeal.

Planning Minister Sir Mark Boleat granted permission after accepting a recommendation from independent planning inspector Nigel McGurk.
The St Martin site was specifically rezoned for affordable housing in the Bridging Island Plan, with the proposed development comprising 30 homes, including 12 two-bedroom and 18 three-bedroom properties.
Under the original application, the homes are intended to be transferred to Jersey Homes Trust, with 55% available for affordable purchase and 45% for social rent.
The scheme also includes a small number of homes for elderly, low-income parishioners through arrangements involving the Sir David Kirch Trust.
A spokesperson for the Infrastructure and Environment Department confirmed that once phases 1A and 1B of the Northern sewer upgrades are complete, the road will be cleared, offering relief to drivers and business owners in the area.
Phases 1A and 1B of the Sion upgrades are still on track for completion by April and May 2027 respectively.