SEWERAGE works are set to be carried out in parts of Trinity over the next three months.
Several roads will be closed temporarily while the Liquid Waste Capital Delivery Team, part of the Infrastructure and Environment Department, carries out works from 6.30am to 6.30pm beginning 13 August.
Les Ruelles will be closed on 13 and 14 August, while Le Rue de Mont Pellier will follow from 17 to 25 August.
From 25 to 26 August, diversions will be in place on La Rue de Moulin du Bas, with La Rue Brûlées closing two days later between 28 and 31 August, and La Rue du Hurel shut to traffic on 29 August, 1 to 5 September, and 22 to 25 September.
La Route de la Trinité will operate under portable traffic signals overnight from 6pm until 6am, starting 29 September and finishing 23 October.
Property access will be maintained where possible, and the department has said that some dates may change due to external factors.