Environment Minister Jonathan Renouf Picture: JON GUEGAN. (36171440)

THE Environment Minister has acknowledged that there is ‘a great deal of work still to do’ to improve the government’s planning services.

The minister was commenting on the release of a detailed plan outlining how he intends to implement recommendations.

The report was produced by former Scottish government chief planner Jim MacKinnon, who was commissioned earlier this year to review the workings of the Island’s planning system.

Mr MacKinnon’s highly critical report – describing ‘ever-more-complex processes, intimidating to an occasional user and frustrating to more frequent stakeholders’ – prompted an immediate response from the minister in May when he undertook to publish a detailed implementation plan to deal with the recommendations, all of which he accepted.

Publishing that plan this week, Deputy Renouf said he was committed to ensuring that the recommendations were met in full and that the department was held accountable, with clear target dates for a series of improvements.

‘I am pleased to now publish this plan and am also pleased to note that a number of the actions are already completed.

‘There is a great deal of work still to do but the publication of this plan sets out the way in which we aim to tackle the issues raised by Mr MacKinnon.

‘I will continue to work with stakeholders to make progress and to keep the public informed as we work to fulfil the actions outlined in the plan,’ the minister said.

A number of steps have already been taken, including the reintroduction of a duty officer at Customer and Local Services enabling Islanders to book appointments for planning and building application advice. A new head of development and land, and a senior regulatory improvement officer for licensing and applications have also recently been appointed.

In the minister’s latest 21-page plan, he sets out the timescales for addressing a range of issues covered in Mr MacKinnon’s report, as follows.

  • Deputy Renouf undertakes, by October, to introduce checklists to provide clear guidelines on what level of information is required for each type of planning application and a service level agreement governing pre-application planning advice.

  • Planning processing agreements, a tool to help manage projects with associated timescales, are due to be introduced by January for certain applications relating to the Island’s housing needs.

  • Relations with both the public and industry are due to be improved through a series of measures including the introduction of a customer service charter by January next year; an industry partnership board which would meet on a quarterly basis, having been established by the end of this year; and publication of a concordat with the development industry to support sustainable economic development, also due to appear by the end of December 2023.

  • A significant issue relates to the introduction of key performance indicators to monitor the department’s performance. A list of those indicators is due to be published by September but the minister acknowledges that a 20-year-old, unsupported computer system ‘significantly limits the ability to extract performance-monitoring data’.

Monitoring of the agreed indicators will only be fully possible when IT improvements are introduced next year, while the full extent of reporting recommended in the review is dependent on additional investment which has been put forward in a bid in the forthcoming Government Plan.